- Client: Trustees of The British Museum
- Main Contractor: Coniston Ltd
- M&E Consultant: TGA Consulting Engineers LLP
- Client Project Manager: Baker Mallet LLP
- Programme: 12 weeks
- Value: £350k

This project involved the provision of new mechanical & electrical services to facilitate the supply and installation by others employed directly by the British Museum of 2 No 800KVA standby generators located in a refurbished boiler house.
A full M & E supply, install, test and commission role was undertaken by Norstead. Scope of services included but not limited to:-
- LV switchgear and distribution system
- Automatic change over panels
- Lighting and general power
- Fire detection
- Emergency voice communication
- Building management system
- External generator exhaust (flue system)
- Lightning protection
- Main earthing & bonding
- Mechanical ventilation – supply & extract
- Bulk storage & fuel system
- Oil leak detection
- Client: Trustees of The British Museum
- Main Contractor: Coniston Ltd
- M&E Consultant: TGA Consulting Engineers LLP
- Client Project Manager: Baker Mallet LLP
- Programme: 12 weeks
- Value: £350k