- Client: John Lewis Partnership
- Consulting Engineer: Lateral Technologies
- Programme: 2 Weeks
- Value: £500K

Norstead were employed to carry out the replacement of 2No DX chillers at the Peter Jones store on the corner of Sloane Square in the heart of London.
Norstead were approached firstly to look at the feasibility of the project to advise on cost and programme. Planning was key to ensure the store was without its full capacity of cooling for an absolute minimum.
The works included the upgrade of existing controls to ensure the new installation was as efficient as possible.
The decommissioning and strip out was programmed so the chiller installation could be carried out on a Sunday when the roads were closed to allow for the craneage operation.
New pipework, power supplies, controls and insulation was completed within 6 days of landing the chillers and the units set to work.
- Client: John Lewis Partnership
- Consulting Engineer: Lateral Technologies
- Programme: 2 Weeks
- Value: £500K