- Client: East & North Herts NHS Trust
- Main Contractor: Geoffrey Osborne Limited
- Consultant: Silcock Dawson & Partners
- Architect: A D Architects
- Programme: 72 weeks
- Value: £2M

A new maternity service facility using the NHS Procure 21 method by Medicinq Osborne, which comprises a new three storey building, main entrance and the refurbishment of an existing single storey building, providing new mechanical services in a hospital environment which imposed constraints with the mechanical design. The new building has 20 delivery rooms, two theatres and a neonatal unit with 30 cots.
Great care and attention was needed throughout the phased change over’s in the project where departments and rooms were misused including a temporary operating theatre and difficult birthing room that were made operational for 11 months while the existing areas was refurbished.
- Client: East & North Herts NHS Trust
- Main Contractor: Geoffrey Osborne Limited
- Consultant: Silcock Dawson & Partners
- Architect: A D Architects
- Programme: 72 weeks