Project Summary:

A Procure 21 plus project providing a new emergency department for the local NHS Trust at the above hospital.

Timescale:

24 Months

Budget:

£4.0m

The project was 24 months in three phases keeping the existing accident and emergency department functioning at all times.

Installation of mechanical and electrical services including chilled water and LTHW services to chilled beams and radiant panels within the ceiling voids.

New roof plant room complete with new plant as detailed below serving the new two storey facility.

  • Air handling units
  • LTHW and Chilled Pump sets and main pipe work
  • BMS control panels and integrated controls system
  • DX cooling condensers to frame and electrical rooms
  • Medical gas plant and associated pipe work to serve the new ward rooms
  • Nurse call systems ,access controls system and all IT infrastructure new fire alarms and smoke control systems

Domestic services have been extended from the main hospital which serves new sanitary ware and brass ware appliances supplied and fitted in to IPS panels within the rooms.

  • Lister Hospital

Services

Mechanical & Electrical Services including:

  • Chilled water
  • LTHW services to chilled beams
  • Radiant panels within the ceiling voids