New Clinical Ward Block, Lister Hospital, Stevenage

Lister Hospital

Project Summary:

A Procure 21 plus project providing a new clinical ward block for the local NHS Trust at Lister hospital.

Timescale:

10 Months

Budget:

£2.3m

Installation of mechanical and domestic services including pumped chilled water and LTHW services to chilled beams and radiant panels within the wards.

A roof plant room complete with new plant as detailed below to serve the new two storey facility.

  • Air handling units
  • LTHW and Chilled Pump sets and main pipe work
  • BMS control panels and integrated controls system
  • DX cooling condensers to frame and electrical rooms
  • Medical gas plant and associated pipe work to serve the new ward rooms
  • Lister Hospital

Services

Mechanical & Domestic Services including:

  • Pumped Chilled Water
  • LTHW Services to chilled beams and radiant panels within Wards